More garden wall progress

I’m still working on the garden wall and hope to get it finished this year. I took a week off work when the weather was suitably dreary and managed 3 courses on the 17m stretch. I’m averaging around 65 bricks a day. The bricks themselves go down fairly quickly – it’s the pointing, cleaning and setting out bricks, and cutting bricks for the piers that seems to take the time.

This weekend I built up the corner and I’m working on the 3m stretch at the back. I like the back. I can go up 4 courses over a weekend.

I’ve balanced some bricks and coping on top of the corner to figure out the height I’m aiming for. I’m aiming 2 bricks higher than the wall I took down but a brick short of the original wall height. I think I will have enough bricks but it is going to be really close.